Water Treatment Plant Update - Work resumes Monday, April 20th
Water Treatment Plant Update
Work set to resume Monday, April 20th, 2026
We are pleased to share an update on the progress of the new water treatment plant project. This important initiative continues to move forward steadily, and we are encouraged by the significant milestones that have been achieved to date.
As of now, approximately 91% of the water plant construction work has been completed. Commissioning activities are currently underway to ensure that all systems are functioning safely and effectively in preparation for full operation. Watermains are swabbed and pressure tested, ready for clean water.
BEI will be returning full time to begin remaining work on Monday, April 20, 2026. Beginning Monday please expect some minor traffic congestion in areas of work. We appreciate your patience during this time as crews work diligently to complete the remaining work. Please remain respectful to workers in our community. Any actions that interfere with or jeopardize this work will put our entire community at risk.
A 14-day testing period is scheduled to begin on May 11th. This phase is critical to confirm that the plant meets all regulatory and performance standards before it is fully brought online.
Water connections to homes are planned to begin at the end of May and will continue into June. Additional information will be shared with affected households in advance to ensure a smooth and coordinated transition.
This project represents a significant step forward in strengthening our community’s infrastructure and ensuring access to safe, reliable drinking water for all members. Our community’s patience, cooperation, courteousness, and respect towards everyone working towards the completion of this project is highly appreciated.
Migwetch,
Public Works
Algonquins of Pikwakanagan First Nation
Distribution System Update
BEI will be returning full time to begin remaining work on April 20, 2026. Beginning Monday please expect some minor traffic congestion in areas of work. BEI will be completing:
· Fire hydrant extensions
· Exposing main piping for chlorination
· Installing 2 water services that were signed over the winter months
· Road repairs
· Completing connection and swabbing of the new health center water service